Progress Summary (Oct 7 - Nov 26)
Completes Progress:
- Final target: 13,223 (per budget)
ⓘ
Overall project target number
- Expected progress (at 119.1/day x 36 days): 4289
ⓘ
Target number we should have reached by now (daily target × days elapsed)
- Current total: 597
ⓘ
Actual cumulative number achieved so far
- Current achievement rate: 13.9%
ⓘ
Achievement rate for current period (current total / expected progress)
- Progress to final target: 4.5%
ⓘ
Progress percentage towards final target (current total / final target)
- Current daily average: 17.7 completes/day
ⓘ
Average daily rate calculated using linear regression
- Gap from daily target: 101.5 completes/day
ⓘ
Difference between target daily rate and current daily rate
- Required catch-up rate: 168.3 completes/day
ⓘ
Daily rate needed from now to reach final target by deadline
Eligibles Progress:
- Final target: 2,729 (per budget)
ⓘ
Overall project target number
- Expected progress (at 24.6/day x 36 days): 885
ⓘ
Target number we should have reached by now (daily target × days elapsed)
- Current total: 132
ⓘ
Actual cumulative number achieved so far
- Current achievement rate: 14.9%
ⓘ
Achievement rate for current period (current total / expected progress)
- Progress to final target: 4.8%
ⓘ
Progress percentage towards final target (current total / final target)
- Current daily average: 4.2 eligibles/day
ⓘ
Average daily rate calculated using linear regression
- Gap from daily target: 20.4 eligibles/day
ⓘ
Difference between target daily rate and current daily rate
- Required catch-up rate: 34.6 eligibles/day
ⓘ
Daily rate needed from now to reach final target by deadline
Trend Projection Note:
- Projections (dashed lines) are based on all data from Oct 7 to Nov 26
- Recent daily rate changes may not be fully reflected in the long-term projection